Monday, July 17, 2023

T302 - Founders' Memorial update Q2 2023 & GBME Shaft

 

2 July 2023 - An aerial view of the contract T302 work site for Founders' Memorial station.

During the release of images by the Land Transport Authority (LTA) of the Thomson-East Coast Line (TEL) phase 4 stations, contract T302's Founders' Memorial station was omitted from the update. This is likely due to the fact that Founders' Memorial was originally intended to be a shell station for fit out at a later stage. As such, its full construction was brought forward to tie in with the opening of the memorial. In lieu of an official update, we bring to you an interim update from July 2023 - sufficiently near enough to June to be considered as a late Q2 2023 update. As an added bonus, we're also covered the Gardens by the Bay Marina East escape shaft in this post.

Sunday, July 9, 2023

T309 - Siglap update Q2 2023

 

8 June 2023 - Exit B of Siglap station, illuminated for night works.

As we press on further east, our updates bring us to contract T309 for the construction of Siglap station. Brought to you by a joint venture between John Holland & Zhen Hua (Singapore) Engineering Pte Ltd. Previously, John Holland had completed Springleaf station and the Tagore box under contract T208 for the Thomson-East Coast Line (TEL) phase 2. Work at Siglap station is progressing well, with some illumination from the station permanent lighting noted. Covered linkways are beginning to go up as well and the road infrastructure & pedestrian paths are slowly being reinstated. We'll delve into these a bit more in our post.

Saturday, July 8, 2023

TEL4 Update by LTA & Minister of Transport

 

Marine Parade station. A TEL train can be seen at the platform.
Source: LTA

Yesterday, the Land Transport Authority (LTA) and Minister of Transport, S Iswaran, teased several images of the 7 stations under phase 4 of the Thomson-East Coast Line (TEL) - Tanjong Rhu, Katong Park, Tanjong Katong, Marine Parade, Marine Terrace, Siglap & Bayshore. These stations are due to open in 2024, with an indicative completion of works date by the end of Q1 of 2024. The line may open shortly after the completion of works. An eighth station that is part of Phase 4 - Founders' Memorial - will open at a later date, closer to the completion of the memorial. The images released by LTA & Minister of Transport are available on our Instagram & Facebook stories as well.

Sunday, July 2, 2023

T308 - Marine Terrace update Q2 2023

 

2 June 2023 - A view of Exit 6, the cooling tower & reinstated open air car park in the evening.

Quite a lot has gone on in the past quarter at contract T308 for the construction of Marine Terrace station. The temporary car park has been closed, the former open air car park has been reinstated, the temporary pedestrian overhead bridge (POB) has been closed & decommissioned and station architectural works are progressing. All within the last quarter alone. Let's unpack how the work has gone & what has been done.

2 July 2023 - A similar view during the day.

Sunday, June 25, 2023

T307 - Marine Parade update Q2 2023

 

2 June 2023 - A view of Exit A seen in the evening, along Marine Parade Road.

Diagram showing the various exits at the station. For ease of reference, we will be using the
lettering as above when referencing to the various exits.
Source: Grand Mercure Roxy

Contract T307 is for the construction of Marine Parade station and associated tunnels is one of the highly anticipated stations along the East Coast stretch of the line Thomson-East Coast Line (TEL). The station will open up connections for the area which includes several hotels, Parkway Parade & I12 Katong malls, the surrounding neighbourhoods & Marine Parade town centre, where the hawker centre can be found. Adjoining the station will be a cut & cover tunnel which houses a cripple siding at track level and a pedestrian retail linkway at concourse level. The cut & cover tunnel will be connected to 4 exits (D - F & Marine Parade CC exit).

Sunday, June 18, 2023

T306 - Tanjong Katong update Q2 2023

 

28 May 2023 - Roof for the pick-up/drop-off  (PUDO) shelter at the station main exit seen during
the evening.

20 May 2023 - The station main exit and PUDO shelter seen during the day.
Image by Seloloving.

Continuing our Q2 update heading east on the Thomson-East Coast Line (TEL), our next stop is Tanjong Katong, formerly known as Amber. Another stacked platform station to fit into the tight station site at Tanjong Katong Road South, the station amazingly features 3 exits. That's more than some of the stations on the Circle or Downtown Lines. Works are at a pretty advanced stage with most of the lighting and station fittings in place. We were not able to observe any signage boards however.

Sunday, June 11, 2023

T305 - Katong Park update Q2 2023

 

28 May 2023 - A view of Exit 1 during the evening.

20 May 2023 - A view of Exit 1 during the day.
Image by Seloloving.

Despite Katong Park being one of the deeper stations along the Thomson-East Coast Line (TEL) phase 4 due to its stacked configuration, the station has progressed quickly with the installation of architectural components. Electrical fittings are also being installed and the station has progressed to using its own permanent lighting to illuminate the work areas. We'd like to thank Seloloving for providing us with some photos to use in this update.