Thursday, November 28, 2024
T316 - Changi bound tunnel completed
›
November 2024 Source: LinkedIn Earlier, we posted that tunneling for the Woodlands-bound tunnel under contract T316 had been completed in ...
Thursday, November 14, 2024
T316 - Woodlands bound tunnel completed
›
27 October 2024 - 1421 tunnel rings completed for the Woodlands-bound tunnel under contract T316. Source: Instagram Recently, the team cam...
Monday, November 11, 2024
TEL5 - A snapshot in October 2024
›
A view of both TEL5 stations in October 2024. Works at the Thomson-East Coast Line phase 5 (TEL5) stations continues on through Q4 of 2024. ...
Friday, August 16, 2024
TEL5 - A snapshot in August 2024
›
A view of some of the exits at Bedok South & Sungei Bedok stations in mid-August 2024. Contracts for Bedok South and Sungei Bedok statio...
Monday, July 29, 2024
T312 - Sungei Bedok update Q2 2024
›
17 June 2024 - A view of Exits 1 and 2 of the station near the junction of Upper East Coast Road with Bedok Road in end-Q2. Similar to Bed...
Monday, July 22, 2024
T311 - Bedok South update Q2 2024
›
17 June 2024 - A view of Exits 2 and 3 in end-Q2. With the Thomson-East Coast Line (TEL)'s phase 4 now open, the focus of the blog wil...
Thursday, July 4, 2024
TEL5 - A snapshot in June 2024
›
17 June 2024 17 June 2024 With the opening of the Thomson-East Coast Line (TEL)'s fourth phase on 23 June, the line is nearly complete a...
›