Thursday, November 28, 2024

T316 - Changi bound tunnel completed

 

November 2024
Source: LinkedIn

Earlier, we posted that tunneling for the Woodlands-bound tunnel under contract T316 had been completed in late October. We have recently come across a photo indicating that tunneling on the Changi-bound (in future Tanah Merah-bound) tunnel was completed this month as well. Congratulations to the Shanghai Tunnel Engineering Co team on the successful completion of both bounds!

This post will also be available on Instagram & Facebook.

Thursday, November 14, 2024

T316 - Woodlands bound tunnel completed

 

27 October 2024 - 1421 tunnel rings completed for the Woodlands-bound tunnel under
contract T316.
Source: Instagram

Recently, the team came across a small update for the TEL Extension contract T316 which was for the construction of twin bored tunnels connecting to the existing Changi Airport MRT station from the vicinity of the future Terminal 5. On the 27th October, tunnel boring works for the Woodlands-bound tunnel were completed with 1421 rings constructed. A hearty congratulations to the Shanghai Tunnel Engineering Co on the achievement!

This post will also be available on Instagram & Facebook on 15 November 2024.

Monday, November 11, 2024

TEL5 - A snapshot in October 2024

A view of both TEL5 stations in October 2024.

Works at the Thomson-East Coast Line phase 5 (TEL5) stations continues on through Q4 of 2024. With the structural works all completed, the works are focused on the architectural and mechanical & electrical elements. We take a closer look at the two stations in greater detail after the jump.