29 September 2025 - A view of the new eastbound platform. Noise barrier installation works had recommenced along the track. |
With the official announcement of the Thomson-East Coast Line extension (TELe), we'll now begin coverage of Tanah Merah station on the East Coast Line Construction Blog as well. Works have been underway at Tanah Merah station since 2016 for the reconfiguration of the station to:
- Increase headway/frequency along the Changi Airport Line (CAL); and
- Connect the East-West Line (EWL) & CAL to the new integrated depot.
To do so, an additional island platform is being added to the station complex so that the existing eastbound EWL track can be diverted to this new platform. The existing track and platform will then be freed up to allow double tracking along the CAL, reducing the bottleneck that restricted frequencies on branch line. Eventually, this would also facilitate the conversion from the line being a branch of the EWL into part of the TEL main line.
Initially due for completion in 2024, pandemic-related delays have seen the completion date of the project pushed to 2026 instead. In December 2025, a service shut down was implemented to allow for one of the reception tracks connecting to the depot to be connected to the eastbound main line tracks. We check in with subsequent progress made on the tracks and station expansion works after the jump.