Sunday, September 18, 2022

T305 - Sneak peak at Katong Park

 

Undated - A view showing the lower platform level & the Woodlands
bound track at the station.
Source: STEC

Earlier when we were doing our recap of the National Day Virtual Tour, we mentioned that we'd drop by again one day to try obtain better pictures of the station progress. We're back with other images and also some throwback glimpses of the station's interior through images sourced online from contractors.

Friday, September 16, 2022

T312 - Sungei Bedok update


19 August 2022 - A view of the station construction site
towards the east.


14 September 2022 - A view of the station construction
site looking eastwards.

Sungei Bedok will become the eastern terminus of both the Downtown and Thomson-East Coast Lines (DTL & TEL) come 2025. According to images released by the Land Transport Authority, the longer trains of the TEL will use the upper platform level while the shorter trains of the DTL will use the lower platforms in the integrated station.

Tuesday, September 13, 2022

T310 - Bayshore progress

19 August 2022 - An overview of the Bayshore station construction site.

Hey everyone, we're back! Due to time constraints during our National Day Virtual Tour of the Thomson-East Coast Line (TEL) phases 4 & 5, we had to skip both Bayshore & Sungei Bedok stations. But soon after, we made another trip down to cover these remaining 2 stations. Do check out the progress of Bayshore station which will have 5 exits. Early last month, Minister Heng Swee Kiat also visited the station and posted a few photos on his Facebook page, showing the station's interior.