Friday, December 29, 2023

TEL4 & 5 year-end update 2023

The 10 stations along the East Coast section of the Thomson-East Coast Line as at end-2023.

 2023 has been an eventful year that has seen the completion of most stations along Phase 4 of the Thomson-East Coast Line (TEL) and the continued work on the stations along Phase 5. With Phase 4 due to come online next year, testing has been underway for some time before the section is handed over to operator SMRT to conduct staff familiarisation and training sessions. While most of the Phase 4 stations are on target with construction, some have sections that still require more work to be done before they can be completed and ready for the temporary occupancy permit (TOP) inspection. We take a look back at 2023 in this final post for TEL of the year.