TEL5 - A snapshot in October 2025

19 October 2025 - A view of the station name sign at Exit 2 of Bedok South station.

When it comes to the Thomson-East Coast Line (TEL)'s phase 5, it can be said that the line is in the more 'boring' phases. This is due to the construction phase being largely completed, hence there are only minor changes taking place at both stations.


TE30 - Bedok South (Contract T311)
In a nutshell: All station exits are completed. Hoarding has been taken down and temporary construction fencing surrounds all station exits and ancillary buildings. The bus stops along Upper East Coast Road have since been opened for public use. The bus stop shelter along Bayshore Drive, however, has been kept under wraps for the time being.


19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

TE31 - Sungei Bedok (Contract T312)
In a nutshell: All station exits appear to be completed, albeit station name signs displaying an empty white background instead of the station names as seen at Bedok South. The road extension that would see Upper East Coast Road connect with Laguna Golf Green is being constructed above the station.

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

19 October 2025

A similar but consolidated (a.k.a. simplified) post will be available on Instagram & Facebook on 15 November 2025.