Thursday, March 30, 2023

T307 - Marine Parade Q1 2023 update

 

23 March 2023 - A view of Exits B and A along Marine Parade Road.

Marine Parade station under contract T307, appears to be the slowest moving among all the 7 stations under the Thomson-East Coast Line (TEL) phase 4 that will be operational next year. That said, the station is definitely not on the level of completion that Great World station along TEL3 was in the months and weeks leading up to that section's opening.

Thursday, March 23, 2023

T306 - Tanjong Katong Q1 2023 update

 

23 February 2023 - A view of Exits A (left) & C (right) from Tanjong Katong Road South.

Moving along eastwards, the next station along the Thomson-East Coast Line (TEL) is Tanjong Katong. The station is located at the intersection of Meyer Road & Tanjong Katong Road South with 3 exits. Exit A is located directly in front of the Aalto condominium, Exit B along Tanjong Katong Road South & Exit C at the intersection of the two roads. The station's exits feature a beige cladding, consistent with the stone influences of other stations designed by DP Architects under contract E1003 - Tanjong Rhu & Katong Park.

Thursday, March 16, 2023

T305 - Katong Park Q1 2023 update

 

23 February 2023 - A view of Katong Park Exit 1 looking westwards along Meyer Road.

Katong Park is the next station on our quarter 1 update for the Thomson-East Coast Line (TEL). Like other stations along this sector, there is noticeable progress with cladding now visible at Exit 2 and also on the ventilation building/cooling tower. Take a look after the jump for more photos!

Thursday, March 9, 2023

T303 - Tanjong Rhu Q1 2023 update

 

23 February 2023 - The 66kV substation under construction.

23 February 2023 - A close up view of the substation.

We are back for your regular dose of Thomson-East Coast Line (TEL) Thursdays. Hope your week has been good just as the progress has been steady on stage 4 of the line. This time, we're over at Tanjong Rhu to check things out as of Q1 2023. Did you know that contract T303 also includes the construction of the 66kV substation? This provides power supply for the line and enables the trains to receive power so that they can move from station to station. Typically such substations are located within depot sites but occasionally, additional support is required along the line.

Wednesday, March 1, 2023

T308 - Marine Terrace Q1 2023 update

 


Marine Terrace station will have 6 exits - all of which are at various stages of construction. Exit A and B are located right in the centre of the station, with Exit A being located along the westbound Marine Parade Road and Exit B directly opposite, along the eastbound Marine Parade Road. Exits C and D are likewise situated across from each other at the eastern end. This brings us to Exits E and F, similarly located opposite each other but on the western end of the station.

Thursday, February 23, 2023

T311 - Bedok South Q1 2023 update

 

19 February 2023 - The structure for Exit 1 along Upper East Coast Road.

Bedok South station, being constructed under contract T311, is the first station along the 5th section of the Thomson-East Coast Line (TEL) and is scheduled to open in 2 years' time. To date, escalators have been installed in 3 of the 5 station exits, with structural works on-going at the remaining 2. For the exits located in the greenfield site, Exit 2 and Exit 3, the metal frame for the station roof is also being installed.

Thursday, February 16, 2023

T309 - Siglap Q1 2023 update

 

11 February 2023 - Substantial cladding work is now visible at the station exits.

We're back along the east coast to check up on progress at the Thomson-East Coast Line (TEL) stations along the eastern stretches after the massive 2022 year-end update previously. Work at contract T309, for the construction of Siglap station without any tunneling work, has ramped up with some major changes at Exits B and D. Cladding is now visible at both exits with substantial parts of the structure now covered in the off-white aluminium cladding.