An overview of TEL stations TE22A to TE25 in September 2023. Top (L - R): TE22A - Founders' Memorial, TE23 - Tanjong Rhu Bottom (L - R): TE24 - Katong Park, TE25 - Tanjong Katong |
|
An overview of TEL stations TE26 to TE29 in September 2023. Top (L - R): TE26 - Marine Parade, TE27 - Marine Terrace Bottom (L - R): TE28 - Siglap, TE29 - Bayshore |
|
An overview of TEL stations TE30 & TE31 in September 2023. Top: TE30 - Bedok South Bottom: TE31 - Sungei Bedok |
Here's a brief update of the status of the 10 stations being built under the East Coast section of the Thomson-East Coast Line (TEL) under phases 4 and 5 of the line.
Phase 4
The stations under phase 4 are wrapping up construction with most architectural elements in place. Completion of works for this section is expected in Q1 2024, thus the contractors have approximately 6 months to go. Marine Parade is the slowest moving of all the stations under this phase.
TE22A - Founders' Memorial (Contract T302)
In a nutshell: More cladding has gone up at the station buildings. As this station will not open with the rest of the stations under the same phase, there is more breathing room at this station site for completion of works.
|
23 September 2023 |
|
23 September 2023 |
TE23 - Tanjong Rhu (Contract T303)
In a nutshell: Majority of the architectural elements are in place. There are also LED signboards installed at the exits that will eventually display train arrival times. Work is now focusing on getting the commuter infrastructure such as linkways, bus stop shelters & pick-up/drop-off shelters ready. Reinstatement around the electrical substation is also underway with the trackworks contractor having vacated the site.
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
TE24 - Katong Park (Contract T305)
In a nutshell: You will be excited to know that this station has the station name signage up at Exit 1 which is located within Katong Park itself. Works are continuing on the covered linkway installation and some hoarding has come down around Exit 2.
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
TE25 - Tanjong Katong (Contract T306)
In a nutshell: Similar to fellow TEL4 stations, a lot of work is now focusing on the commuter facilities infrastructure such as bus stop shelters and covered linkways. Majority of the station buildings appear complete and the LED signboards are visible within the station exit buildings.
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
TE26 - Marine Parade (Contract T307)
In a nutshell: Works are still focused on the station exit and ancillary buildings - these are mostly cladding and installation of the metal roofs. Architectural works and the installation of mechanical & electrical components still has some way to go at certain exits. The exits connected to the station box are more advanced than those connected to the retail subway.
|
3 September 2023 |
|
3 September 2023 |
|
3 September 2023 |
TE27 - Marine Terrace (Contract T308)
In a nutshell: Works are taking place to tidy up the road facilities while construction of commuter facilities infrastructure continues. LED signboards can be seen within the station exit buildings.
|
3 September 2023 |
|
3 September 2023 |
|
3 September 2023 |
|
3 September 2023 |
TE28 - Siglap (Contract T309)
In a nutshell: The station structures are pretty much complete. Work on the sheltered linkways and other commuter facilities in the main focus now.
|
3 September 2023 |
|
3 September 2023 |
|
3 September 2023 |
|
3 September 2023 |
TE29 - Bayshore (Contract T310)
In a nutshell: The 5 station exits are ready. Like other stations along this section, commuter facilities infrastructure is the main focus of works.
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
Phase 5
Stations under this phase of the line have an expected completion of works date in Q1 2025, hence they are at a slower state of completion as compared to those under phase 4 of the line.
TE30 - Bedok South (Contract T311)
In a nutshell: Works are ongoing for the station exits roof structure at Exits 1, 4 & 5. Reinstatement works are ongoing along Upper East Coast Road when the road diversion is decommissioned.
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
TE31 - Sungei Bedok (Contract T312)
In a nutshell: Work is still focused on the roof of the various station exits and has not moved on to architectural elements like cladding as yet.
|
23 September 2023 |
|
23 September 2023 |
|
23 September 2023 |
We will be following up with Q3 updates in time to come, so do stay tuned to look out for these once Q3 comes to a close. In the mean time, do check out our other blogs & Instagram channel for more updates on other lines too.
A similar but consolidated (a.k.a. simplified) post will be available on Instagram & Facebook.