17 June 2024 - A view of Exits 1 and 2 of the station near the junction of Upper East Coast Road with Bedok Road in end-Q2. |
Similar to Bedok South station, works over the past quarter for contract T312 have seen a larger focus on architectural works rather than structural works. Various fittings have gone in to the station's 4 exits, allowing them to resemble station exits more closely. It is also interesting to see the architectural features as they begin appearing.
27 May 2024 - A view of Exit 2 near the junction of Upper East Coast Road and Bedok Road in mid-Q2. |
Upper East Coast Road is set to be extended further east and connect with Laguna Golf Green once the works for the contract are completed. At the moment, the junction between Bedok Road and Upper East Coast Road still exists as a bend and has not been converted into a T-junction yet. Looking eastwards, the ancillary buildings for the station can be seen. Over the past quarter, at least one of the buildings has been painted in the station's paint scheme, somewhat reminiscent of the scheme used for Kaki Bukit station along the Downtown Line.
27 May 2024 - A view eastwards along the future extension of Upper East Coast Road towards Laguna Golf Green in mid-Q2. Ancillary buildings for the station can be seen in the distance. |
17 June 2024 - A view eastwards of the future road extension as of end-Q2. |
17 June 2024 - A view of the station's ancillary buildings in the distance as of end-Q2. |
27 May 2024 - Another view of the station's ancillary buildings in mid-Q2. |
17 June 2024 - A close up view of the station's ancillary buildings, one since painted, as of end-Q2. |
Works at Exits 1 and 2 are the most visible as Exits 3 and 4 are located within the worksite area that will see the extension of Upper East Coast Road and is hence not publicly accessible. In addition, due to worksite boundary reconfigurations, the portion of pathway where the exits could be viewed from previously has since been diverted in end-Q2, obscuring the view of these 2 exits.
Over at Exits 1 and 2, on the western end of the station, works have seen the continued installation of the exits' fittings such as staircase railings, glass panels, cladding and ceiling panels. As the exits are located near publicly accessible areas with pedestrian pathways nearby, it is fairly easy to get a decent look at the stations. Covered linkways are also in progress to connect the exits with nearby bus stop shelters and pick-up/drop-off shelters. These adopt a similar design to those being constructed at neighbouring Bedok South station.
27 May 2024 - A view of works at Exit 1 in mid-Q2. |
27 May 2024 - Work ongoing for the entrance canopy for Exit 1. Bollards were being installed here as well. |
27 May 2024 - A view westwards along the reinstated Upper East Coast Road in mid-Q2. |
17 June 2024 - Works at Exit 1 in end-Q2. |
17 June 2024 - A view of the exit's entrance canopy and entrance plaza area. |
17 June 2024 - Installed glass panels with green protective tape visible. |
17 June 2024 - Ceiling panels have also been installed at the exit while tiles are onsite. |
17 June 2024 - Covered linkways being installed to the pick-up/drop-off shelter. |
17 June 2024 - An overview of progress at Exit 1 at the end of Q2. |
17 June 2024 - An overview of progress at Exit 2 in end-Q2. |
17 June 2024 - Exit 2 behind the temporary barriers along Upper East Coast Road. A covered linkway is being built to connect the exit with the bus stop shelter. |
17 June 2024 - Another view of the covered linkway and bus stop shelters near Exit 2. |
With works progressing steadily and the section's opening pushed back to 2026, there should be sufficient time for the contractor to complete any outstanding works. Do check back as we periodically update on the section's progress, although this may be relegated to monthly snapshot updates rather than the deep dives based on contracts that we have been doing previously.
No comments:
Post a Comment