Tuesday, April 23, 2019

T309 - Siglap progress update

Contract T309 is for the construction of Siglap station only, without any associated tunnels. The station will have 4 exits and will be built as a civil defence shelter. The assigned contractor is a joint venture by John Holland and Zhen Hua. Previously, John Holland successfully delivered the Jalan Besar station on the Downtown Line through another join venture.

30 September 2016 - Ground breaking at contract T309 site
Source: John Holland

Since ground breaking of the East Coast Line in July 2016, the John Holland - Zhen Hua join venture had their own site ground breaking ceremony in September 2016 to kick off works at T309. The station will be built using the top-down cut-and-cover method.

16 January 2017 - Contract T309 site works commencing.
Source: John Holland
Slowly but surely, over the years, the site has undergone numerous traffic diversions to facilitate the construction of the station's retaining walls. Works have progressed to the construction of the temporary openings to allow subsequent excavation to the lower levels while concurrent casting of the slab progresses westwards.

23 September 2017 - A view of the work site at night.
Source: Ted Choo
30 March 2019 - Preparations for slab casting.
Source: Laguna Park - Singapore
10 April 2019 - Heavy machinery on site.

10 April 2019 - One of the few temporary openings in the roof slab.

10 April 2019 - Temporary opening with telescopic excavator.

10 April 2019 - Roof slab after pouring completed and waiting for concrete curing.
Upcoming works at the site should include the continued casting of the roof slab and temporary openings. Excavation work will then progress downwards while concurrent casting of the various levels takes place.