Sunday, May 24, 2026

TEL - A snapshot in May 2026

The TEL5 stations at Bedok South & Sungei Bedok and TELe Tanah Merah station as of mid-May
2026.

With the Circle Line early closures & late openings coming to an end, the next line in queue for such works is the Thomson-East Coast Line (TEL) for phase 5 testing & integration works. We took a look at the vicinity of the 2 remaining stations due to open later this year and at the progress of works at Tanah Merah's new exits. Find out more after the jump.

Sunday, December 14, 2025

T315 - Tanah Merah post-make over

The week-long shut down to reconfigure tracks at Tanah Merah station completed a day early last week, allowing for the resumption of train services. With the expanded Tanah Merah station now since reopened for a week, we take a look at the changes made to the station as part of the upgrade. 

Saturday, December 6, 2025

T315 - Progress of works at Tanah Merah

6 December 2025 - An aerial view of the expanded Tanah Merah station with new viaducts visible.

Works at Tanah Merah station have been ongoing for a week now. These works would facilitate reconfiguration of the tracks along the East-West Line (EWL) to allow eastbound trains to call at a new platform in the expanded station. The new platform would allow for increased frequencies along the Changi Airport Line (CAL), which will be subsumed into the Thomson-East Coast Line (TEL) in a few years' time.

With publicly accessible vantage points limited, we were only able to catch views of the majority of the works affecting the eastbound tracks although the works also involved the westbound tracks. In view of this, the update mainly focuses on the works affecting the eastbound tracks.

Thursday, November 27, 2025

T315 - A last look at Tanah Merah before transformation

A map of the Tanah Merah station, with exits renumbered following the station upgrade.

You've probably heard all about it by now - East-West Line (EWL), no service, 29th November to 8th December, shuttle buses, alternative routes. Another round of track work modifications are here, to enable the expansion of Tanah Merah station. We're here to repeat most of the information again, but also to add on what may be happening to the best of our knowledge and update the status of works before the big shut down.

Friday, October 31, 2025

TEL5 - A snapshot in October 2025

19 October 2025 - A view of the station name sign at Exit 2 of Bedok South station.

When it comes to the Thomson-East Coast Line (TEL)'s phase 5, it can be said that the line is in the more 'boring' phases. This is due to the construction phase being largely completed, hence there are only minor changes taking place at both stations.

Thursday, October 2, 2025

T315 - A Tanah Merah update in September 2025

 

29 September 2025 - A view of the new eastbound platform. Noise barrier installation works had
recommenced along the track.

With the official announcement of the Thomson-East Coast Line extension (TELe), we'll now begin coverage of Tanah Merah station on the East Coast Line Construction Blog as well. Works have been underway at Tanah Merah station since 2016 for the reconfiguration of the station to:

  • Increase headway/frequency along the Changi Airport Line (CAL); and
  • Connect the East-West Line (EWL) & CAL to the new integrated depot.
To do so, an additional island platform is being added to the station complex so that the existing eastbound EWL track can be diverted to this new platform. The existing track and platform will then be freed up to allow double tracking along the CAL, reducing the bottleneck that restricted frequencies on branch line. Eventually, this would also facilitate the conversion from the line being a branch of the EWL into part of the TEL main line.



Initially due for completion in 2024, pandemic-related delays have seen the completion date of the project pushed to 2026 instead. In December 2025, a service shut down was implemented to allow for one of the reception tracks connecting to the depot to be connected to the eastbound main line tracks. We check in with subsequent progress made on the tracks and station expansion works after the jump.

Saturday, July 26, 2025

TELe - Officially announced

Alignment map of the Thomson-East Coast Line Extension (TELe).
Source: LTA

Yesterday, the Land Transport Authority (LTA) announced a 14km extension to the Thomson-East Coast Line (TEL). The extension consists of 1 new station at Changi Terminal 5 and new tunnels of 7.6km that will connect the 6th phase of the line to the existing stations along the Changi Airport Line (CAL). The three existing stations along the 6.4km long CAL will be absorbed into the TEL as well.

Tuesday, July 1, 2025

TEL5 - A snapshot in June 2025

A view of the two TEL5 stations as of June 2025.

With half the year since past, how have works on the Thomson-East Coast Line (TEL)'s final phase progressed? As the stations have largely been completed, changes these days appear to be more minor in nature as compared to station progress along the Jurong Region Line (JRL) or at Xilin station on the Downtown Line (DTL) for example. Join us as we explore the slight progress seen in the first half of the year after the jump.

Thursday, March 13, 2025

TEL5 - Aerial snapshot in March 2025

9 March 2025 - An aerial view of Bedok South station.

Recently, en route back from Kuala Lumpur, we managed to get some great views of the two Thomson-East Coast Line phase 5 stations from the air. Despite the team's semi-frequent travel, various factors need to come together in order for us to get these shots - arrival timing, direction of landing, window seat, clear windows and weather - just to name a few.

Sunday, February 23, 2025

TEL5 - A snapshot in February 2025

A view of the two phase 5 stations of the Thomson-East Coast Line in February 2025.
Top (L - R) : TE30 - Bedok South (Exit 3, Exit 2)
Bottom (L - R) : TE31 - Sungei Bedok (Exit 1, Exit 2)

Its been a while since we've updated on the progress of the phase 5 station of the Thomson-East Coast Line (TEL). This has largely been due to the two stations being at advanced stages of completion, that there isn't much by the way of progress. Nonetheless, we'll do some periodic updates to check in at the stations and let you know the details of the changes that have taken place on site. As always, details after the jump.

Thursday, November 28, 2024

T316 - Changi bound tunnel completed

 

November 2024
Source: LinkedIn

Earlier, we posted that tunneling for the Woodlands-bound tunnel under contract T316 had been completed in late October. We have recently come across a photo indicating that tunneling on the Changi-bound (in future Tanah Merah-bound) tunnel was completed this month as well. Congratulations to the Shanghai Tunnel Engineering Co team on the successful completion of both bounds!

This post will also be available on Instagram & Facebook.

Thursday, November 14, 2024

T316 - Woodlands bound tunnel completed

 

27 October 2024 - 1421 tunnel rings completed for the Woodlands-bound tunnel under
contract T316.
Source: Instagram

Recently, the team came across a small update for the TEL Extension contract T316 which was for the construction of twin bored tunnels connecting to the existing Changi Airport MRT station from the vicinity of the future Terminal 5. On the 27th October, tunnel boring works for the Woodlands-bound tunnel were completed with 1421 rings constructed. A hearty congratulations to the Shanghai Tunnel Engineering Co on the achievement!

This post will also be available on Instagram & Facebook on 15 November 2024.

Monday, November 11, 2024

TEL5 - A snapshot in October 2024

A view of both TEL5 stations in October 2024.

Works at the Thomson-East Coast Line phase 5 (TEL5) stations continues on through Q4 of 2024. With the structural works all completed, the works are focused on the architectural and mechanical & electrical elements. We take a closer look at the two stations in greater detail after the jump.

Friday, August 16, 2024

TEL5 - A snapshot in August 2024

A view of some of the exits at Bedok South & Sungei Bedok stations in mid-August 2024.

Contracts for Bedok South and Sungei Bedok stations on phase 5 of the Thomson-East Coast Line (TEL) may have had a one year extension to their deadlines, but work on the stations has not slowed down a bit. A recent visit in the middle of the month saw that works were still pushing ahead at both stations, with the exit structures and ancillary buildings really getting dressed up now. With structural completion now behind the project teams, work has shifted to focus on the finer architectural details of the stations' facilities.

Monday, July 29, 2024

T312 - Sungei Bedok update Q2 2024

 

17 June 2024 - A view of Exits 1 and 2 of the station near the junction of Upper East Coast Road
with Bedok Road in end-Q2.

Similar to Bedok South station, works over the past quarter for contract T312 have seen a larger focus on architectural works rather than structural works. Various fittings have gone in to the station's 4 exits, allowing them to resemble station exits more closely. It is also interesting to see the architectural features as they begin appearing.

Monday, July 22, 2024

T311 - Bedok South update Q2 2024

 

17 June 2024 - A view of Exits 2 and 3 in end-Q2.

With the Thomson-East Coast Line (TEL)'s phase 4 now open, the focus of the blog will shift to cover the remaining 2 stations along the line's phase 5 at Bedok South & Sungei Bedok. Over the past quarter, works have continued in the vicinity of the Bedok South station. These focus on the architectural elements of the station's exits and supporting infrastructure such as roads and commuter facilities.

Thursday, July 4, 2024

TEL5 - A snapshot in June 2024

17 June 2024

17 June 2024

With the opening of the Thomson-East Coast Line (TEL)'s fourth phase on 23 June, the line is nearly complete as initially envisioned following the merger of the former Thomson and Eastern Region Lines. This leaves the remaining initial fifth phase of 2 stations at Bedok South & Sungei Bedok under construction till their opening in 2026. Over the past month, the contractors have continued to work on the station's exits, commuter facilities and road reinstatement.

Saturday, June 22, 2024

A review of the TEL4

 

21 June 2024 - A view of our small exhibit at the Friends of Land Transport booth at Marine
Parade station during the TEL4 Preview event.

The Thomson-East Coast Line (TEL)'s fourth phase was off to a roaring start this Friday with 9 hours of free rides during the preview event. Visitors to the event got to experience riding the trains on the line for free, while exploring the 7 stations stretching from Tanjong Rhu to Bayshore. Trains operated on an isolated loop along the stretch with trains terminating at Platform A at both termini. A separate shuttle train linked the TEL4's Tanjong Rhu station with TEL3's Garden by the Bay at both station's Platform B. The Land Transport Authority (LTA) really did go all out to make the event possible and accessible for everyone.

Tuesday, June 18, 2024

TEL4 - A walk down memory lane

9 May 2024

9 May 2024

27 May 2024

27 May 2024

27 May 2024

27 May 2024

27 May 2024

With the Thomson - East Coast Line (TEL)'s fourth phase about to open at the turn of the week, we thought it'd be a great time to take a walk down memory lane and look back at how far along the line has come. Join us as we take a stroll along the East Coast through time.

Tuesday, June 11, 2024

TEL4 - Retail units for lease

 

Floor plan for Tanjong Rhu station concourse level.
Source: Stellar Lifestyle

Thomson-East Coast Line (TEL)'s operator SMRT has recently added 4 stations along TEL4 to their list of retail units available for lease. The units available are located at Tanjong Rhu, Marine Parade, Siglap & Bayshore stations. We understand that retail units may also be available at Tanjong Katong and Marine Terrace stations although these are not currently listed on the SMRT retail arm's website.

With the listing of the retail units, the various floor plans of the stations have also become available for viewing. The available date provided on the website indicates "Stage 4" currently (which is not a date, but okay), and may roughly indicate that the units will be available in conjunction with the section's opening after 23 June 2024.