T308 - Marine Terrace Q1 2023 update

 


Marine Terrace station will have 6 exits - all of which are at various stages of construction. Exit A and B are located right in the centre of the station, with Exit A being located along the westbound Marine Parade Road and Exit B directly opposite, along the eastbound Marine Parade Road. Exits C and D are likewise situated across from each other at the eastern end. This brings us to Exits E and F, similarly located opposite each other but on the western end of the station.


Exit A
This exit was one of the first to emerge for the station and will be located smack in the heart of Marine Terrace housing estate. The metal roof frame for the exit has been installed for some time now and cladding works are becoming more pronounced.

11 February 2023 - Exit A seen from a distance along the westbound carriageway of Marine Parade
Road.

11 February 2023

11 February 2023

11 February 2023

11 February 2023

Exit B
Located across the road from Exit A, this exit is having a part of the concrete wall being cast. Other works that have been completed including the installation of the metal roof frame while cladding works have just begun. Although not apparent in this image, cladding is being installed at the base of the exit. It presumably will be installed upwards.

11 February 2023

Exit D
This exit is located in close proximity to St Patrick's school and is in the midst of having its metal roof frame being installed. The escalators, previously installed, sit below tarpaulin to protect the equipment from the recent wet and rainy weather.

11 February 2023

Exit C
This exit is also located near a school and care had to be taken to ensure that the works do not interfere with the nearby school's operations. Like Exit D across the road, metal roof frames are being installed before other works such as cladding and tiling can proceed.

11 February 2023

11 February 2023

19 February 2023

19 February 2023

Exit E
One of the last exits of the station, cladding works have commenced at the station exit. Whilst not visible from the road junction, a small portion of the concrete structure has been adorned with the grey cladding on the side that faces the Thomson-East Coast Line Project Information Centre.

11 February 2023

11 February 2023 - A view of the on-going cladding works.

Exit F
The sixth exit of the station also is currently undergoing cladding works. Similar to that of Exit E, the cladding works commence from the base of the exit and will, over time, be installed further upwards.

11 February 2023

Cooling Tower / Ventilation Shaft
The Cooling Tower and/or Ventilation Shaft for the station is located near the junction of Marine Terrace & Marine Parade Road. Equipment is being installed to allow for ventilation of the station areas once operational.

11 February 2023

11 February 2023

19 February 2023

19 February 2023

19 February 2023


Progress on stage 4 of the TEL seems to be progressing well. Join us as we continue to cover the progress at other sites along the TEL in Q1 of 2023.