Saturday, December 10, 2022

T307 - 2022 Year end update

 

21 November 2022 - Exit A along Marine Parade Road, opposite Parkway
Parade shopping mall just outside Roxy Square.

25 November 2022 - Exit C next to Parkway Centre.

3 December 2022 - Exit B located at the junction of Marine Parade &
Joo Chiat Roads.

Marine Parade station is located right at the heart of the busy neighbourhood and right next to Parkway Parade mall. Directly abutting the station is a cripple siding which will also serve as an underground commercial linkway. Shops are envisioned to be leased out here offering benefits to users as they commute from the station to their destinations. In addition to the commercial linkway, we also understand that as the Marine Parade Community Club (CC) undergoes refurbishment, a new exit via the basement will be constructed to allow for visitors to connect directly to the MRT station. This exit will likely open in the future once the CC is reopened after reconstruction.


21 November 2022 - Exit D located next to block 74.

21 November 2022 - Exit D.

25 November 2022 - Metal frame for the lift being installed.

3 December 2022 - Exit D with the metal frame for the lift installed.

3 December 2022

3 December 2022

3 December 2022 - Exit D will connect to the commercial linkway than
to the station directly.

21 November 2022 - Exit F at the junction of Marine Parade & Still Roads.

21 November 2022

21 November 2022 - Exit F

21 November 2022 - Exit E which is located opposite Exit D

21 November 2022

21 November 2022 - Exit B

21 November 2022

21 November 2022

21 November 2022

Like at other stations, works are focused at the station exits. Thus far, it appears that the 3 exits that will connect directly to the station concourse - Exits A, B & C - have escalators installed. Exits A & C also have the lift shaft frames installed as well. As Exit B is an exit that is integrated with a cooling tower or ventilation equipment, the lift shaft here will be constructed from concrete instead.

The remaining exits at the station will connect to the commercial linkway and are at less advanced stages of construction. These exits also potentially do not have their escalators installed in yet. With the progress noted at surface level, the contractor is attempting to complete Exits A, B & C first before the remaining Exits D, E & F. This may also help the station proper to be completed at a comparable rate to other stations on the line and allow for the commencement of test and trial runs than if all exits were to be completed together.

Information panel at the PIC.



3D architectural model showing the station cross section.

A cross section view of Exit E.

A cross section view of Exit F.

A close up view of Exit F.

A close up view of Exit E.

A cross section view of the main station concourse & platform.

The 3D architectural model for Marine Parade station shows that Exits A, B & C will be connected to the station proper whilst Exits D, E & F will connect to the commercial linkway. The model also shows a cross section of the cripple siding with the commercial linkway above.

We look forward to further progress at the station in the coming year when cladding is likely to go up at the exits.

This post is also available on Instagram.